Algiers Metro | Algeria


Completed in: 2025

The Algiers Metro project that involved SELI Overseas aims to connect the city center to the airport. In fact, it extends the Metro line between the El Harrach station located in the historic center of the city and the airport area where the Aéroport station will be built. The project consists in the construction of the subway tunnel with a mechanized method using an EPB type TBM having an excavation diameter of 10.5m. The TBM has passed through 8 stations already built and 10 ventilation shafts with transversal connection tunnel, along a route that extends for approximately 9.5 km.

Technical data


TBM excavation, lining and backfilling for approximate 8,60 km with a EPB TBM.
 
Excavation performed in two steps:
‐ Excavation of approx. 5,7 km from the Starting station to the Airport station;
‐ Dismantling the TBM and transport from the Airport station to the Starting station;
– Excavation from the starting station of the remaining 3,8 km;

Excavation diameter

10,5 m


Tunnel length

9,5 Km


Geology

Sand, Silt, Clay, Weak Sandstone and Weak Limestone


Type of support

Precast concrete segment


Client

Cosider Travaux Publics


Other featured projects


Val Lemme | Italy


Radimero | Italy


Serravalle | Italy


Lonato | Italy


Suffolk County | USA


Tsuen Wan | Hong Kong


Poza Honda | Ecuador


Beles Tailrace | Ethiopia


Beles Headrace | Ethiopia


Kishanganga | India


El Alto | Panama


Xe-Pian Xe-Namnoy | Laos


CCD Grande Dixence | Switzerland


Vancouver Underground – Canada Line | Canada


Milan Underground Line 5 | Italy


Doha Underground – Gold Line | Qatar


Algiers Underground | Algeria


Abdalajis East | Spain


Railway to Jerusalem – Line C | Israel


Lodz Railway Tunnel | Poland


Los Bronces | Chile


Cairo Underground | Egypt


High Speed railway Messina – Catania | Italy


High Speed railway Fortezza-Ponte Gardena | Brennero