Excavation diameter
7.20 m
Tunnel length
5,100 m
Geology
Granite and tuff
Type of support
Prefabricated segments
Completed in
2010
Client
Government of Hong Kong
Rainwater drainage to prevent flooding in Hong Kong during the rainy season.
This tunnel work was carried out using a Telescopic Double Shield TBM in the very hard granites characteristic of the Asian metropolis, with the job being completed on time.
§In this project, SELI Overseas confirmed its unique experience and expertise in rock tunnelling using shielded TBMs.
In Hong Kong alone, this was the fifth project successfully completed by SELI Overseas since 1990.
Other featured projects

Val Lemme | Italy

Radimero | Italy

Serravalle | Italy

Lonato | Italy

Suffolk County | USA

Tsuen Wan | Hong Kong

Poza Honda | Ecuador

Beles Tailrace | Ethiopia

Beles Headrace | Ethiopia

Kishanganga | India

El Alto | Panama

Xe-Pian Xe-Namnoy | Laos

CCD Grande Dixence | Switzerland

Vancouver Underground – Canada Line | Canada

Milan Underground Line 5 | Italy

Doha Underground – Gold Line | Qatar

Algiers Underground | Algeria

Abdalajis East | Spain

Railway to Jerusalem – Line C | Israel

Lodz Railway Tunnel | Poland

Los Bronces | Chile

Cairo Underground | Egypt

High Speed railway Messina – Catania | Italy